A builder approached us through our single-project contract works form for a new attached dual-occupancy in western Sydney. The project was a two-storey duplex with a single garage, valued at around $800,000, and it began with demolishing the structure already on the site.
The build was expected to run about 15 months, with roughly 60% of the work handled by subcontractors - carpenters, bricklayers, concreters and plumbers. They needed cover in place from the commencement date.